Learning Objectives

By the end of this chapter, you will be able to:

  • Sequence ERP phases from chartering to post go live and name each output.
  • Group fit gap, go live, and deployment choices by risk and control.
  • Explain module integration in procure to pay and hire to retire.
  • Apply success factors and TCO to a Nepal case with VAT, CBMS, and Shrawan fiscal year.

Buying Is Easy, Implementing Is Hard

Software is bought in a day. Use is earned over months. An ERP brings its own view of how purchase, stock, sale, and payment should flow. Davenport (1998) warned that an enterprise system imposes its logic on strategy and culture. Implementation decides where the firm bends to the package, where the package bends to the firm, and how people shift from sheets to shared posting.

Markus and Tanis (2000) frame the journey as chartering, project, shakedown, and onward and upward. The nine phases below sit inside that cycle.

Grouped Phases

flowchart LR
    P["1.Planning"] --> R["2.Requirements"]
    R --> FG["3.Fit gap"] --> D["4.Design"]
    D --> M["5.Migration"] --> T["6.Testing"]
    T --> TR["7.Training"] --> C["8.Cutover"] --> S["9.Support"]
    style C fill:#1565c0,color:#fff

Figure 1: Phases Overlap In Practice

Phase Key work Output
1 Planning Case, scope, sponsor, budget, partner Charter and plan
2 Requirements Map as is and to be, legal needs Process maps
3 Fit gap Compare need to standard, choose close method Fit gap register
4 Design Chart of accounts, VAT codes, roles, workflows Configured system
5 Migration Extract, clean, load masters and balances Clean masters, tie out
6 Testing Unit, integration, UAT, performance, parallel payroll Signed results
7 Training Role based, super users, guides Ready users
8 Cutover Freeze old entries, final load, go decision Live system
9 Support Hypercare, fixes, monitoring, improvement Stable operation

Fit Gap Discipline

Four ways close a gap, cheapest first: change process, configure, work around, customize. Nah, Lau and Kuang (2001) urge minimum customization because code must be retested at each upgrade.

Register, Nepali distributor, Magh 2081:

Requirement Fit or gap Decision
Sales order and delivery Fit Standard
13 percent VAT with buyer PAN Fit Configure tax code
Bikram Sambat dates Gap Localization add on
Shrawan to Ashadh fiscal year Gap or fit Configure periods
Enlisted e billing and CBMS Gap IRD enlisted connector
Keep old discount sheet Gap Change to price lists

Grouped Go Live Choices

Approach Switch Advantage Risk Suits
Big bang All at once Shortest, no bridge Whole firm exposed Small, simple firm
Phased By module or site Lower risk per step Longer, temporary interfaces Multi branch
Parallel Both run, compare Safety net Double entry, overload Payroll, first close
Pilot One site as trial Real test May not represent all Similar branches

Pilot at Pokhara then phased to other sites, with one parallel payroll cycle, is a common hybrid.

On Premise Versus Cloud SaaS

SaaS per NIST SP 800-145 runs provider apps on cloud infra without consumer managing servers or OS.

Factor On premise SaaS
Cost Upfront licence plus hardware Subscription per user
Infra Firm runs servers and backup Provider runs infra, needs internet
Customization Deep, harder to upgrade Config and extensions within limits
Upgrades Firm schedules Provider cadence
Data Own premises Provider centres, check contract
Internet Works offline locally Needs backup link and offline fallback

Nepal note: outside Kathmandu Valley, a second link and an offline billing procedure belong in the SaaS plan from day one.

Modules And Integration

Module Functions Posts to
Finance Ledger, payables, receivables, tax All post here
HR and payroll Employee, attendance, leave, payroll Finance expense
Procurement Requisitions, orders Inventory and finance
Inventory Stock, receipts, transfers, valuation Finance value, sales availability
Sales Quotations, orders, pricing, delivery Inventory reservation, finance revenue
Manufacturing BOM, work orders, costing Inventory and finance
CRM Leads, cases, campaigns Sales and finance
flowchart LR
    PR["Requisition"] --> PO["Order"] --> GR["Receipt"] --> INV["Invoice 3 way"] --> PAY["Pay"]
    HI["Hire"] --> AT["Attendance"] --> PY["Payroll"] --> GL["Ledger"]

Figure 2: Procure To Pay With Three Way Match And Hire To Retire

Three way match blocks payment when order, receipt, and invoice differ on quantity or price. One database makes the check possible.

Success Factors And Failure Causes

Nah et al (2001) list 11 factors: teamwork, change programme, top support, business plan, minimum customization, project management, monitoring, communication, testing, champion, and legacy readiness. Importance shifts by phase. Holland and Light (1999) group strategic factors (vision, ERP strategy, top support, schedule) and tactical factors (consultation, personnel, process change, acceptance, monitoring, communication, troubleshooting).

Failure Missing factor
Seen as IT only Top support, champion
No clear goals Business plan, monitoring
Heavy customization Minimum customization
Dirty masters Legacy control, testing
Weak end to end tests Testing
Late generic training Change management

Change Management

  • Stakeholder analysis on who gains and who loses load.
  • Visible sponsorship by owner at steering.
  • Super users per department for design, test, and peer support.
  • Communication plan by role.
  • Training with own data near go live, Nepali guides where needed.
  • Reinforcement: retire sheets on a fixed date, track adoption.

TCO

TCO is all cost over five years, not licence alone. Often missed items are internal staff time and the dip after go live.

Category Examples
Software, implementation, infra Subscription or licence, partner fees, hosting or servers
Data, customization, testing Cleansing, e billing and CBMS connector, UAT effort
Training, staff, support Materials, seconded key users and backfill, helpdesk, upgrades
Risk reserve Contingency and productivity dip

Nepal Rules

  • VAT: Act 2052 Section 7 sets 13 percent, zero rated items in schedule. Rules exempt registration at or below NPR 50 lakh goods or NPR 20 lakh services or mixed in last twelve months. ERP must post correct codes and VAT registers.
  • E billing: IRD Procedure 2074 allows only enlisted billing software. Verify on ird.gov.np.
  • CBMS: Notice 4 Baisakh 2083 requires taxpayers above NPR 20 crore to issue electronic invoices linked to CBMS at issue time, except banks not issuing direct invoices. Thresholds change, verify latest notice.
  • Fiscal year: Shrawan 1 to end of Ashadh. Many firms align go live to Shrawan 1 for clean opening balances. Bikram Sambat dates often needed on documents.

Worked Example: Gandaki Agro Traders, BS 2081

Gandaki Agro distributes seed and tools from Pokhara with branches in Butwal and Bharatpur. Sheets at branches, accounting at head office, Excel payroll. Stock mismatches, close takes two weeks, turnover near CBMS threshold.

Plan, Mangsir 2081: pilot at Pokhara on Shrawan 1, 2082 for finance, inventory, sales, procurement, two months, then phased to Butwal and Bharatpur. Payroll parallel in Shrawan. SaaS chosen due to no IT staff, with backup link and offline billing fallback at each branch. Risks watched: data quality with physical count before migration, top support with owner as chair and a full time lead, and change with one super user per branch.

Self-check

Try This Gandaki SaaS proposal, BS 2081: subscription Rs. 55,000 per month for 12 users, setup Rs. 380,000, training Rs. 90,000, migration Rs. 110,000. Year 2 ongoing is subscription plus 15 percent of setup for support and upgrades. Close shortens from 14 to 4 days, saving 10 days of two staff at Rs. 3,000 per day each month. Compute Year 1 TCO, Year 2 cost, monthly saving, and months to recover Year 1 from that saving.

Answers: Year 1 = 55,000×12 = 660,000 + 380,000 + 90,000 + 110,000 = Rs. 1,240,000. Year 2 = 660,000 + 57,000 = Rs. 717,000. Monthly saving = 10×2×3,000 = Rs. 60,000. Recovery = 1,240,000 ÷ 60,000 = 20.7 months from this item alone, faster with variance and delivery gains.

Summary

Implementation turns package into working record through nine phases. Fit gap favors process change and configuration over code. Go live trades speed for risk. Modules meet in procure to pay and hire to retire. Sponsorship, clear vision, clean data, testing, and change decide success. In Nepal the plan must also meet VAT, enlisted billing, CBMS, and Shrawan fiscal discipline with connectivity designed from start.

Key Takeaways

  • Nine phases, with migration, testing, training overlapping.
  • Close gaps by process or config before customization.
  • Big bang, phased, parallel, and pilot balance time and risk.
  • SaaS lowers infra load but needs internet resilience.
  • One database links procure to pay and hire to retire.
  • Failures trace to weak sponsorship, unclear goals, dirty data, and poor training.
  • TCO includes staff time and post go live dip.

Exercises

Short answer

  1. List nine phases in order.
  2. Name four ways to close a gap, cheapest first.
  3. Distinguish big bang and phased on risk.
  4. What is CBMS and who must connect.

Long answer

  1. Trace Gandaki Agro implementation from chartering to support on a Shrawan 1 timeline with fit gap, go live choice, SaaS decision, and TCO in NPR. Cite Markus and Tanis, Holland and Light, Nah et al.
  2. Compare on premise and SaaS for a Nepali manufacturer with branches on VAT and CBMS duties. Compute two year TCO from given numbers and state the risk if internet is single sourced.

References

  • Davenport, T. H. (1998). Harvard Business Review, 76(4), 121–131.
  • Holland and Light (1999). IEEE Software, 16(3), 30–36. doi:10.1109/52.765784
  • Markus and Tanis (2000). In Zmud (Ed.), Framing the Domains of IT Management, 173–207.
  • Nah et al (2001). Business Process Management Journal, 7(3), 285–296.
  • Somers and Nelson (2001). HICSS-34.
  • Mell and Grance (2011). NIST SP 800-145.
  • IRD. Notice 4 Baisakh 2083 and enlisted list via ird.gov.np.
  • VAT Act 2052 Section 7 and VAT Rules 2053 via ird.gov.np.